Sri Lanka Urban Multi-hazard Disaster Mitigation Project
(SLUMDMP) |
In September1997 CHPB was selected by the USAID for the management of the Sri Lanka Urban Multi-Hazard Disaster Mitigation Project
(SLUMDMP), which is the Sri Lanka country project in a programme involving several Asian countries under the Asian Urban Disaster Mitigation Programme
(AUDMP). This programme is implemented by the Asian Disaster Preparedness Center
(ADPC) in Bangkok, Thailand and funded by the
USAID. The Sri Lankan project is implemented by the CHPB in collaboration with the National Building Research Organisation
(NBRO) and the Urban Development Authority
(UDA) providing the technical inputs. The project includes demonstration, training, information and networking activities related to urban disasters. Apart from the demonstration project activities involving activities related to mitigation of natural hazards in the Ratnapura MC, there is a considerable training component in the project, which is carried out by the CHPB. Disaster mitigation activities are mostly concerned with integration of natural hazard aspect in the planning process and guidelines for construction in hazard prone areas. Therefore the project involves a major training component for engineers and technical officers of local authorities, and also planners in the
UDA.
The project goal:
Reduced natural disaster vulnerability of urban populations, infrastructure,
lifeline facilities and shelter in Sri Lanka.
The project objective:
Establishment of sustainable public and private sector mechanisms for disaster
mitigation in targeted urban areas of Sri Lanka

Project Location :
Ratnapura MC Area, Sabargamuwa
Province
|
Demonstration Phase: |
Start
date: 15 September, 1997 |
|
|
End
date: 31 May, 2001 |
|
|
|
|
Total
Project Cost: |
US $
318,217 |
|
Total USAID Cost: |
US $
256,182 |
|
Total Counterpart: |
US $
62,035 (19 % of total) |
More Details
After the main project
activities were completed in February 2000, the Replication Phase of the Project
started in June 2000, which too was completed by the end of November 2002.
During this Phase too activities were carried out in collaboration with other
agencies (Cost sharing basis or full cost borne by them).
Project Location :
Kandy MC and Nawalapitiya UCCentral
Province, Colombo Municipal Council (CMC)- Western Province
|
Replication Phase: |
Start
Date : 1st June 2000 (No cost extension) Grant Completion date :
30th May 2001(No cost extension) |
|
|
1st
Grant Extension : 31st December 2001 (No cost extension) 2nd
Grant Extension : 31st March 2002 (No cost extension) 3rd
: 30th September 2002 (No cost extension) 4th
: 30th September 2002 (Grant amount increased
by USD 1,755) 5th
: 30th November 2002 (No cost extension) 6th
" : 31st March 2003 (No cost extension)
|
|
Total USAID cost: |
US $
70,573 - Grant Amount |
|
Total Counterpart: |
US $
77,195 (52% of total)
|
|
|
Total
= US$ 147,768 |
More Details
The Consolidation Phase which
started on 1st April 2003 and the scheduled duration was 5 months.
The activities are planned to be completed by the proposed second extended date
of completion, i.e. 31st October 2003.
Project Location: Kandy
MC, 12 Local Authorities (Dompe, Kotikawatta/ Mulleriyawa, Biyagam, Seethawaka,
Homagama,Kaduwela, Wattala, Mahara, Kelaniya Pradeshiya Sabhas and
Seethawakapura, Wattala, Peliyagoda and Kollonnawa UCC) along Kelani River from
Avissawella to Colombo Medawewa at Arachchikattuwa Pradeshiya Sabha, Puttalam
District in North Western Provice Eastern Province, Central Province.
|
Consolidation Phase: |
Start
Date: 1st April 2003 Grant Completion date 31st
August 2003
|
| |
1st
Grant Extension :30th September 2003 (No cost extension) 2nd
Grant Extension :31st October 2003 (No cost extension)
|
|
Cost: |
US $
29,044 (Amount Received) US $ 35,000 (Approved Grant Amount) |
|
Total USAID Cost: |
US $
33,212 (53.35% of total) |
|
Total Counterpart: |
Total
= US $ 62,256 |
More Details
The Extension Proposal
detailed in this report is based on the recommendations of the USAID Monitoring
Mission who met the SLUMDMP officials in Bali and also visited Sri Lanka in
September 2002. Some of the recommendations were already been taken up in the
Consolidation Phase.
Project Location : Kandy MC,
Ratnapura MC, 12 Local Authorities (Dompe, Kotikawatta/Mulleriyawa, Biyagam,
Seethawaka, Homagama,Kaduwela, Wattala, Mahara, Kelaniya Pradeshiya Sabhas and
Seethawakapura, Wattala, Peliyagoda and Kollonnawa UCC) along Kelani River from
Avissawella to Colombo Karukapane Chilaw UC/Arachchikattuwa Pradeshiya Sabha,
Puttalam District in North Western Provice Eastern Province, Central Province,
Disaster affected districts namely, Ratnapura, Kalutara, Galle, Matara and
Hambantota.
|
Extension Phase: |
Start
Date: 5th January 2003 Grant Completion date 31st
December 2004
|
| |
|
|
Cost: |
US $
50,000 (SLR 4,775,000) - Approved Grant Amount |
|
Total USAID Cost: |
US $
50,000 |
|
Total Counterpart: |
SLR
1,929,100 (US$ 20,306) |
|
Total
= US$ 70,306 |
More
Details
|